Our live diagrams — every chart drawn from the same sourced records that power the map. Press play, scrub the timeline, watch the fight move.
KPIs and the four panels above are drawn from our register of 20 tracked projects, built from municipal agendas & minutes, MPSC filings, and utility disclosures. Status & region reflect the latest public record. Disclosed load counts only the 6 of 20 projects that have published a nameplate figure — the real total runs higher. The grid mix shows Michigan's 2024 statewide generation (EIA), the pool new load draws on — not per-project sourcing. Full methodology →
33 communities have paused data-center development. Press play to watch the wave spread, month by month.
Each dot is a Michigan community that adopted a formal data-center moratorium, pause, or ban, placed at the community and dated to the month the measure passed. Built from municipal ordinances and meeting minutes; a community is counted once, at its first pause.
Every community weighted by what it faces right now — active projects, local pauses, and upcoming hearings. Bigger, hotter dots = more pressure.
Pressure score = active projects + adopted local pauses + hearings scheduled in the next 30 days, summed per community. It is an editorial index for triage — a relative signal of where to look, not an official measurement. Dot size and color scale with the score.
Cumulative disclosed nameplate load (MW) across tracked projects, plotted by the month each figure entered the public record. Only projects with a published load appear; the 14 undisclosed projects are excluded, so the curve is a floor, not a ceiling. Home-equivalent uses the U.S. average of ~10.8 MWh/home/yr.